Refinery Shutdown Crude Unit Upgrade
Completion Date
5/98
Services
Process
Mechanical
Industry
Refining & Chemical
Location
East Coast
This project involved upgrading the east crude unit to increase capacity by 20%. The project entailed detail design and approximately 60 sub projects required for a three week turnaround. The schedule was three months in duration leading up to the outage. Projects involved piping design, structural steel and foundation design, electrical engineering, construction cost estimating and planning, and field construction support.